Mestre by pass

PROJECT DETAILS

  • Employer Commissario Delegato per emergenza socio-economico-ambientale della viabilità di Mestre
  • Country Italy
  • Sector transport, roads and motorways
  • Area Veneto
  • Contract value 109,600,000 euro (Annual Report 2014)
  • Locality Mestre (Venezia)
  • Finished work in 04 2010
  • Partecipation 12%

PROJECT DESCRIPTION

Design and construction of 32,3 km of three-lane motorway, emergency lane and three interconnections: two with A4 motorway Venice-Padova-Trieste and A27 motorway Mestre-Belluno.

The main works entailed in the definitive project are: 4 viaducts, for a total length of 1,515m; 9 trench sections, of which 8 are partially covered, for an overall length of 10,200m; 14 river crossings with single span bridges (between 25m and 35m long); 15 overpasses and 22 underpasses of the motorway.

Furthermore 3 motorway stations and 3 new barriers at Dolo, Mogliano Veneto and Quarto d’Altino have been realized.