Ausa Basin

PROJECT DETAILS

  • Employer Hera Spa
  • Country Italy
  • Sector ecology and environment, water purificaton plants
  • Area Emilia-Romagna
  • Contract value € 19,055,351
  • Locality Rimini
  • Finished work in 12 2020
  • Partecipation 42.35%

PROJECT DESCRIPTION

The project envisages the detailed design and the construction of two sewage collection tanks at the Ausa Basin closing section. The first tank is used as a detention basin for the Ausa, while the second collects first flush rainwater. These tanks are equipped with all the electrical and mechanical systems required for the emptying and subdivision of the tanks. Architectural and landscaping works is then carried out to return Piazzale Kennedy to the local community.

PHOTO

< Back to all PROJECTS